Facade insulation — Buildings Programme (VD)
Contribution per insulated m², depending on energy requirements met.
Grants for thermal insulation of the building envelope (walls, roof) via the Buildings Programme.
www.leprogrammebatiments.chFacade insulation · Vevey

At a glance
Small project
CHF 20'000 – CHF 41'400
Typical project
CHF 36'800 – CHF 73'000
Large project
CHF 62'100 – CHF 120'400
| Project | Quantity | Low | High | Per unit |
|---|---|---|---|---|
| Small project | 110 m² | CHF 20'000 | CHF 41'400 | CHF 300 |
| Typical project | 220 m² | CHF 36'800 | CHF 73'000 | CHF 200 |
| Large project | 385 m² | CHF 62'100 | CHF 120'400 | CHF 200 |
Computed with our estimator for Vevey (regional factor included), standard finish. Only the project size changes.
Included
Not included
In Vevey, the federal building register lists 1'246 residential buildings and 11'124 dwellings. These municipal benchmarks help put your home in context, but do not replace an individual assessment.
84 % built before 1980
Construction year does not reveal past renovations: check the current insulation condition.
63 % · Gas
This distribution describes recorded buildings, not your system's consumption or efficiency.
31.2 % of buildings mix housing with shops or offices.
For renovation planning in Vevey, official building register data shows only partial coverage, with 9 protected buildings identified among 196 known structures out of 1171 total entries, necessitating early consultation with local authorities regarding permits. Furthermore, the median house volume is 958.5 cubic meters based on the SIA 416 standard, derived from 62 measurements among 298 recorded houses. Understanding this volume is vital for homeowners, as it dictates the scale of necessary heating and insulation works.
Source : Registre fédéral des bâtiments et des logements (RegBL), OFS, 2026. Existing residential buildings; percentages of recorded values.
Located on the shores of Lake Geneva at an altitude of 383 meters, Vevey experiences significant heating needs.
With approximately 2544 heating degree-days and about 22 frost days per year, local real estate is subject to climatic stresses that impact energy consumption.3 °C.
Undertaking these works is particularly relevant if you notice cold walls or mold, which are signs of a thermal bridge break.
The city of Vevey, which has been awarded the 'Energy City GOLD' label since 2012, actively encourages the energy transition through its municipal Climate Plan.
The 'Vevey Rénove' program, launched in 2022, aims to stimulate the renovation of the existing building stock.
By insulating your facade, you are not only contributing to the longevity of your property, but you are also participating in the local energy dynamic aimed at rationalizing consumption over the long term.
This is an ideal time to enhance your property while meeting current environmental challenges in the canton of Vaud.
The technique of facade insulation generally relies on the External Thermal Insulation Composite System (ETICS).
The choice of insulation material (stone wool, expanded polystyrene, or bio-sourced materials) depends on the desired performance, water vapor permeability, and your budget.
Each material has its own thermal resistance properties, and choosing an appropriate thickness is essential to maximize energy savings while respecting the existing architectural envelope of your building in Vevey.
The project can vary depending on the quality level desired, particularly regarding the finish: mineral plaster, wood siding, or composite panels.
In addition to the insulation itself, the quality of junctions (doors, windows, roof) is crucial for ensuring airtightness. Also, consider reflecting on solar protection and aesthetics, especially if your building is old.
It is advisable to consult a specialist to evaluate the interaction between the chosen insulation and your wall's load-bearing structure to avoid any problems with internal condensation or degradation of facade materials over time.
The real estate stock in Vevey is marked by great diversity, ranging from historic homes in the city center to more recent constructions on the outskirts.
Before 1990, many building materials, including insulation, adhesives, or certain plasters, may contain asbestos. Before any drilling or demolition, technical expertise is essential to identify the presence of hazardous substances.
Furthermore, older buildings often feature outdated electrical or plumbing networks that should be checked before being encapsulated behind new insulation.
Old facades, often made of stone masonry or brick, require special moisture management. An ill-adapted insulation could trap moisture inside the wall and cause major structural degradation.
It is crucial to analyze the permeability of existing materials before adding an insulation layer. In addition, managing thermal bridges at balconies and cornices is a classic difficulty on buildings in Vevey.
A tailored approach, respecting building physics, is the only guarantee to avoid costly damage after works, especially since many structures are in direct contact with the damp conditions of the lakeside.
This guide does not establish a permit exemption. If your building or area is protected, check the constraints specific to your project.
For your insulation work, financial aid is available through the Buildings Program of the canton of Vaud. This program provides contributions per insulated m², calculated according to the energy requirements achieved.
A golden rule must be followed : the subsidy application must be submitted and validated before the start of renovation work. Once work has begun, it is generally too late to apply for this aid.
The official website of the Buildings Program allows you to check eligibility conditions and submit your file.
On the tax side, the canton of Vaud allows for the deduction of costs aimed at saving energy. These investments, which concern the replacement of obsolete elements or the addition of insulation, are 100% deductible.
Note that in the case of a public subsidy, only the portion remaining at your expense can be deducted. If the costs are high, the balance can be carried over to the two following tax periods.
You have the choice between deducting actual costs or the flat-rate deduction for the maintenance of your property.
It is strongly advised to consult a tax specialist to optimize your declaration according to your personal situation and the nature of your work, in order to fully benefit from these legal tax relief mechanisms.
The planning of a facade insulation site in Vevey requires anticipating the seasons, particularly due to winter temperatures. The installation of scaffolding is an essential prerequisite step and represents a significant part of the overall cost.
It is strategic to group your work : if you are planning facade insulation, take the opportunity to replace your windows or renovate your roof, as the access is already secured.
This allows for significant economies of scale on the installation of lifting equipment.
The typical process begins with the diagnosis and the submission of permits, followed by the installation of scaffolding. Then, the steps of installing the insulation, applying the reinforcement, and finishing (plaster or cladding) follow.
Weather conditions, especially marked frost periods, can dictate the drying rate of the plasters. It is preferable to schedule this work during temperate periods to ensure the durability of the applied materials.
Once the facade is finalized, the dismantling of the scaffolding marks the end of this transformation phase.
Anticipate these steps several months in advance to obtain the necessary authorizations and book the craftsmen, as availability may be limited during seasons favorable to building.
To avoid disappointment, do not start any work before receiving a written response regarding your subsidy application. A classic mistake is to neglect the condition of the substrates, which can lead to moisture infiltration after insulation.
Ensure that the contractor checks the integrity of the structure before fixing the panels. Never skip the opinion of municipal services for protected zones, as the risk of having to redo the facade at your own expense is real.
Finally, do not focus only on the price; the quality of materials and the reliability of the company are decisive for the lifespan of your investment.
Checklist before requesting quotes : 1. Check if your building is listed in a protected zone (ISOS) with the municipality. 2. Have an energy audit performed by a certified professional. 3. Identify if asbestos testing is necessary given the age of the building.
4. Plan to group your work (roof, windows) to make the scaffolding profitable. 5. Submit your subsidy application to the Buildings Program before signing any contract. 6. Ask for detailed quotes specifying the brand of materials and the type of finish. 7.
Require a schedule that takes into account seasonal climatic constraints.
1. Estimate
Set a budget range with the estimator.
2. Grants
Apply before work starts.
3. Quotes
Compare at least 3 quotes.
4. Permit
Check with the municipality whether a permit is needed.
5. Works
Follow the site and do a written handover.
Contribution per insulated m², depending on energy requirements met.
Grants for thermal insulation of the building envelope (walls, roof) via the Buildings Programme.
www.leprogrammebatiments.chCheck amounts and conditions with the provider before signing: apply before work starts in most cases.
1800 Vevey · about 0 km
Grisoni-Zaugg S.A. is a company specialized in general building construction, civil engineering, and demolition works.
groupe-grisoni.ch1800 Vevey · about 0 km
Vevey-based company specializing in interior and exterior painting, plastering, and renovation projects for residential and commercial clients.
une-histoire-de-couleur.ch1800 Vevey · about 0 km
Alessio Gianfreda Sàrl specializes in painting, plastering, and interior and exterior renovation works in Vevey.
alessiogianfreda.ch1800 Vevey · about 0 km
Posse Riviera SA specializes in painting, plastering, wall coverings, and building renovation works.
posse.chSuggestions from the commercial register by distance and activity. Not an endorsement or partnership.
The first step is to contact the urban planning department to check heritage constraints (ISOS). Then, submit your subsidy application to the Buildings Program before requesting any quotes.
Yes, but under strict conditions. You must obtain a building permit and find a technical solution that respects the exterior appearance, often after arbitration by the authorities.
Yes, the canton of Vaud allows a 100% tax deduction for investments aimed at saving energy. The deduction is calculated on the net portion remaining at your expense.
This makes the cost of scaffolding profitable, which is a major expense for the site. Craftsmen also gain efficiency by working in one go.
Yes, it is essential to opt for a system allowing good moisture management due to lakeside conditions. A permeability analysis is recommended.
You must check for the presence of asbestos in old materials before any drilling. Technical expertise is advised to avoid any health risks.
Imperatively before the start of renovation work. Once the site has started, it is no longer possible to claim this financial aid.
Altitude
383 m
Heating degree days
2'544 Kj/an
20/12 °C
Frost days
22 jours/an
Solar irradiation
1'352 kWh/m²/an
horizontal
Winter design temperature
-2.3 °C
1er percentile des minimales
Mean temperature
12.2 °C
Source : swisstopo – service d'altitude (MNT) · Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024)
Source : vevey.ch
These rules apply across the whole canton, not only in this town.
Permits
Tax deductions
Source : Règlement sur la déduction des frais relatifs aux immeubles privés (RDFIP)